Neighborhood Architects proposes replacing the vacant house between Domino's and Revival Cafe with a 6-story apartment building with commercial space on the ground floor and 16 residential units (3 affordable) on the upper floors.
The original design was a 4-story building with 10 residential units (2 affordable).Β After receiving city approvals, the developer's preliminary site work contractor discovered excavating the basement would be unusually expensiveβabout $500,000βbecause of the local soil and the need to avoid damaging the foundation of Revival.
This is a problem because the developer needs 10 units for adequate revenue, but the density factor required by Somerville Zoning Ordinance means the square footage of the basement is needed for the project to be legal.
The developer could ask for a hardship variance to eliminate the basement (which would also be bad for commercial tenants), or they could ask for a hardship variance or zoning map change to allow a 6-story building (with additional units to cover the unexpected cost).
The developer met with the DSNC Board on September 28th, 2026, and presented the 6-story design to the entire DSNC membership at our October 26th general meeting.
Currently (as of September 22nd, 2026), the building is abandoned and boarded up.
π¦ Status: Awaiting approval for redesign (Original design was approved by Planning Board, Urban Design Commission, and Historic Preservation Commission)
βοΈ 4-6 Stories
π No off-street parking, eliminates existing driveway
π² 10 off-street bicycle parking spaces
π Developer project webpage
π City project webpage (incl. plans and shadow study)
Pablo Picker, Developer
Picker Construction LLC
βοΈ PickerConstruction@gmail.com
Lance Davis, Ward 6 Councilor
The City held a neighborhood meeting about the project on January 27th (π Developer report)
The Urban Design Commission voted to recommend the project with recommendations on February 11th (π Official recommendations)
The City held a neighborhood meeting about the project on February 27th.Β (π Meeting notice; π Developer report; π DSNC notes)
The developer published a Transportation Action Plan on March 6th (modified on March 28th and in May)
The Urban Design Commission signed its recommendation on May 13th
The Planning Board held a hearing on the project on August 7th
The Planning Board continued the hearing and voted to approve on August 21st
The Planning Board signed its approval document on September 3rd
The developer's preliminary site work contractor discovered excavating the basement would be unusually expensive (about $500,000) because of the soil conditions and need to avoid damaging the foundation of Revival
The DSNC Board met with the developer on September 28th
At the October 26th DSNC general meeting, Pablo Picker and attorney Adam Dash said they needed more units to make the project economically viable (from 10 β 16 total units, 2 β 3 affordable units, 4 β 6 stories).Β That would require a zoning change from the city.Β Architect Paul Miller presented new designs.Β Adam Dash presented the shadow study for the new design.Β (π Presentation)